sample report generated from MS Project using msp_html.pl on Thu Feb 22 14:10:26 2007

The Perl utility msp_html.pl produces project reports based on input from MS Project 2000. To see the options, run the following command:

     perl msp_html.pl -help

The input file is created from Project by doing the following:

When you save, do "save as" and select "CSV" as the type.

From now on, you can just select "msp_due" as the map when saving as "CSV".

Legend
n Hover over to reveal special note
+ Click on to expand/collapse milestone
Indicates a finished task
Joe D Hover over an individual's name to reveal commit percentage.
11/14/06 Hover over a date to reveal the day of the week.
92 Hover over to reveal the predecessor.

Progress Graph

Milestone Target   Complete
Gather Documentation Tue 3/14/04   100%
Meet with Vendor Wed 4/19/04   100%
Create H/W Estimates Mon 5/22/04   100%
Decision for Development Tue 6/6/04   100%
Planning Meeting for Solaris 10 Fri 6/9/04   100%
Gather Statistics Wed 6/14/04   100%
Solaris Pilot Wed 3/1/04   100%
Blackboard Pilot Wed 3/1/04   35%

Project Detail

ID i % Comp Task Name Duration Start Finish Pred Resource Names
1 100% Gather Documentation 1 day? 03/14/04 03/14/04 none Don L
2  n 100% Meet with Vendor 1 day? 04/19/04 04/19/04 none Team
3 100% Create H/W Estimates 3 days 05/22/04 05/22/04 none Harry S
4 100% Decision for Development 1 day? 06/06/04 06/06/04 none Team
5 100% Planning Meeting for Solaris 10 1 day? 06/09/04 06/09/04 none Team
6 100% Gather Statistics 28 days 06/14/04 06/14/04 none Harry S
7 100% + Solaris Pilot 102 days 03/01/04 03/01/04 none Don L
46     35% + Blackboard Pilot 363 days? 03/01/04 03/01/04 none Team